Saturday, December 21, 2024

Significant Progress Achieved in Building Oakville Sports Complex

Posted in
on
Construction on the Sixteen Mile sports Complex in Oakville is progressing, with significant developments including the installation of cross-laminated timber decking on the ceiling and the completion of the pool deck. The Town of Oakville announced updates on the expansion project through a video on social media, highlighting upcoming work such as concrete pours for the first floor and ongoing roof reinforcement in arena Four. The facility will feature various amenities, including aquatic facilities, a fitness center, a library, and a variety of outdoor recreational spaces. Set to open in 2025, the complex aims to incorporate sustainable design practices and accessibility features. The first phase, which includes sports fields and a cricket pitch, was completed earlier this year.

Read More